Transmission Line Works


Transmission Line Works


Till date, the Contractor has completed check survey, soil investigation works and design of the tower and is currently working on the construction of foundation of the towers. Manufacturing of most of the tower parts has been completed in India and China and being imported to the Project site gradually. Furthermore, tower accessories including insulator, OPGW, conductor, etc. has already been manufactured, tested and is in process of delivery to the Project site.

The construction license of the transmission line has been acquired. The land acquisition works for 20 tower angle points (AP) has been completed and the land acquisition works for the remaining locations along with the RoW clearance is in progress. The erection of stub and foundation concreting works have been completed in 19 locations which is almost 80% of total foundation works whereas the foundation works is ongoing in 1 location. The tower erection works have already started at AP16 as the tower parts are being delivered to the Project site.